I just recieved some answers from FIRST correcting some mistakes on the playing field blueprints.
1. Center Barrier, P16, upright supports, should be 1-1/4" Schedule 40 Aluminum, quantity should be 6 and length should be 16".
2. Bridge counter wieght support pipe assembly. The 1" pipe is inserted flush in the 1-1/4" pipe and the 3/4" pipe is inserted about 3" in the 1" pipe. Note: use 6, 3# weights on each support.
3. The quantity for PVC1, goal, horizontal supports should be 16.
Engineer on team #365, Miracle of Engineering, from Avon Grove HS and DuPont.
I just recieved some answers from FIRST correcting some mistakes on the playing field blueprints.
1. Center Barrier, P16, upright supports, should be 1-1/4" Schedule 40 Aluminum, quantity should be 6 and length should be 16".
2. Bridge counter wieght support pipe assembly. The 1" pipe is inserted flush in the 1-1/4" pipe and the 3/4" pipe is inserted about 3" in the 1" pipe. Note: use 6, 3# weights on each support.
3. The quantity for PVC1, goal, horizontal supports should be 16.