Team 254 - 2014 Build Blog + Tech Binder
 
Hi everyone,

Although it may be a bit late, we would like to release this year's Build Blog and Technical Binder. Both these resources are now publicly available on our website.

We tried to keep the Technical Binder simple and use it mostly as a visual aid when explaining the robot to judges, so if you have any questions or want more specifications, feel free to ask!

wasayanwer97 08-07-2014 20:30

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Wow. This is awesome!
Thanks for releasing these!

Andrew Lawrence 08-07-2014 20:44

Re: Team 254 - 2014 Build Blog + Tech Binder
 
New CAD computer one day and the 254 Build Blog + Tech Binder the next? Christmas in July really does exist.

On a more serious note, I always love reading these and am forever thankful to Team 254 for documenting and releasing such an amazing learning resource each year.

coalhot 08-07-2014 21:04

Re: Team 254 - 2014 Build Blog + Tech Binder
 
One of my favorite parts of the summer. There goes an evening! (not complaining) :D

AllenGregoryIV 08-07-2014 21:30

Re: Team 254 - 2014 Build Blog + Tech Binder
 
I love the technical binder. That's the prettiest FRC publication I have ever seen and one the most useful. Thank you

seg9585 08-07-2014 21:43

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Can I ask a logistical question here -- reading the blog (which is amazing, by the way), how were you able to accomplish just the amount of time dedication to the team during the build season? I counted a total of 3 Rest Days.

How can the mentors juggle it with work and family, and avoid burnout? How do the students handle it with homework, midterms, etc?
Our team has had to basically shut down for a week in late January because of midterm exams. Putting in 8 hours a day every single day just isn't practical.

artK 09-07-2014 00:35

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Quote:

Originally Posted by seg9585 (Post 1392529)
Can I ask a logistical question here -- reading the blog (which is amazing, by the way), how were you able to accomplish just the amount of time dedication to the team during the build season? I counted a total of 3 Rest Days.

How can the mentors juggle it with work and family, and avoid burnout? How do the students handle it with homework, midterms, etc?
Our team has had to basically shut down for a week in late January because of midterm exams. Putting in 8 hours a day every single day just isn't practical.

We were able to do what we did without a large amount of burnout mostly because we had a large enough team that the load would not be placed on just a few individuals.

During the build season we had four rest days (these are all in the blog), all Mondays, excluding the first Monday, when we just starting the season, and the last one, which was during a week off from school so the students who wanted to were able to come. After we bagged up the robot, we all took a couple of days off. Also after bag and tag, our blog posts became less frequent (as did attendance), and so days of rest were not officially noted on the blog, though Mondays were still days of rest.

Additionally, lab safety policies put a cap on occupants, so the team limited signups for the lab to 3 days per week for students, though this was only enforced on weekdays when more students wanted to come, so I would often be there 4-5 days per week during build season. This limit allowed me to choose which days I would not attend, and so I would check my schedule to align that for when I have a test (as a sidenote, Bellarmine did not have official midterms, just big tests spread throughout the semester, so we dodged that bullet). I often was at the lab between 5 and 10 most days, and since school got out at about 3, I had a daily 2 hour block for homework. Any additional homework was done in the mornings before school.

The key to balancing robotics, school, and the rest of one's life (so as to avoid burnout) from my experience has been making a schedule and sticking to it. When I say "lab between 5 and 10" I meant it, the latest I ever left was 10:36. Schedules are also easiest to keep when they are regular, so I got into a very nice groove of school, homework, lab, sleep, repeat throughout the build season.

Some numbers to go along with this (Lab times courtesy of our sign-in system, which is in the cloud):
  • Total hours: 225.8 (6th most for 254)
  • Average times: 5.0 hours
  • Standard Deviation: 2.0 hours
  • Median/Mode times: 4.3 hours
  • Longest/Shortest times: 11.8, 2.4

Torrance 09-07-2014 00:46

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Quote:

Originally Posted by seg9585 (Post 1392529)
Can I ask a logistical question here -- reading the blog (which is amazing, by the way), how were you able to accomplish just the amount of time dedication to the team during the build season? I counted a total of 3 Rest Days.

How can the mentors juggle it with work and family, and avoid burnout? How do the students handle it with homework, midterms, etc?
Our team has had to basically shut down for a week in late January because of midterm exams. Putting in 8 hours a day every single day just isn't practical.

Not only do we have a really large team (90 students, at least 30 in the lab every night) but we also have lots of mentors to distribute the workload. I have no idea how the mentors balance robotics with work/family, they are truly amazing.

Also, builds are usually not 8 hours long. Weekday builds start at 5:30 (mentors get off work), we spend an hour eating dinner together, and then most students leave around 10 or 11pm. Weekend builds go from 1pm to about the same time but sometimes end as late as 3am. However, students will sometimes come in shifts for weekend builds.

Our school does not give that many midterms, especially to underclassmen, so we don't take time off for that.

Despite all that, it does take a tremendous amount of time to be a member of this team, but in the end I think it all pays off!

Cory 09-07-2014 01:12

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Until the end of build I don't think we had a single true break day. We had 3 Mondays that were "breaks" where the majority of the students and some mentors didn't come, but we still had some mentors and students there for all of them.

We took a few true break days post ship and worked reduced numbers of hours relative to during build, but still quite a lot.

This season was infinitely better than last year. 2013 was a nightmare. It took so much work to integrate all our subsystems and to complete the hanger. We also had fewer mentors, which took a toll on us. There was a 4 day stretch during the last full week of build where I was at the lab from 4 PM until no earlier than 4 AM, with one night until around 6:30 in the morning and another where we didn't go home. This year we didn't have a single night that was as bad as any of those.

Joel Glidden 09-07-2014 11:55

Re: Team 254 - 2014 Build Blog + Tech Binder
 
I'd love to get a link at your Trello board (boards?) from this season. Would you guys be willing to share a link?

Pat Fairbank 09-07-2014 13:22

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Quote:

Originally Posted by Joel Glidden (Post 1392572)
I'd love to get a link at your Trello board (boards?) from this season. Would you guys be willing to share a link?

We ended up ditching Trello partway through build season (due to difficulty of keeping it in sync) and went with a more analog solution.

Joel Glidden 09-07-2014 13:28

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Thanks. We had decent success using Trello for our drawing creation, review, release, and mfg workflow. We had about the same experience as you did trying to use it for our overall activities.

Nathan Rossi 09-07-2014 16:04

Re: Team 254 - 2014 Build Blog + Tech Binder
 
This is an excellent resource, thanks for sharing! Now, if only I could get the rest of my team to read this...

BrendanB 09-07-2014 19:00

Re: Team 254 - 2014 Build Blog + Tech Binder
 
Quote:

Originally Posted by Pat Fairbank (Post 1392576)
We ended up ditching Trello partway through build season (due to difficulty of keeping it in sync) and went with a more analog solution.

Good idea. :rolleyes:

We gave Trello a shot this past year and it was much easier to implement during the fall as there was more time to keep it up to date and time to check it. It almost needs its own staff of a few students to keep it up to date and clear/archive/move around old cards/boards. We found it is a great tool for the offseason when meetings are infrequent and commitment levels are lower.

Michael Hill 09-07-2014 23:18

Re: Team 254 - 2014 Build Blog + Tech Binder
 
I'm curious, in the Tech Binder, I'm looking at the Excel Spreadsheets...

For Seconds to Completion and Probability of Completion, are those what you think the "Average" team will do or what you think your team can do?