Re: How often do you worry you're behind?
Well, during the first week of build season we lost 2 days to snow. Saturday, we only had 2 students and 2 adults. Then we lost Monday due to the holiday. Nothing happened on Tuesday for some reason(s) {exams being one of them} and then today only 2 people were able to work (only one student, me) again due to exams. Are we behind? In my opinion, no, but we will be at this pace. We have a good minibot prototype and a frame with wheels (but no chains, sprockets, or motors). It seems like nobody plans on going to any meetings this week, of the three years I have been on the team this is the most I've seen exams affect attendance. I really hope the reason is truly because of exams and not the 90 minute gap between exams and the meeting or "because nobody else will be there" because 1) I don't like being called nobody, and 2) because that shows a serious lack of motivation and interest.