Drive has been done for 2 weeks, Superstructure, ball conveyance, entrance, and exit manipulators have been built for a week, but we have been tweaking them. Bridge lowering device is done and needs mounting, It was prototyped but the final version has not been tested, We had to add a pneumatic to get the ball storage mechanism to work, so we need to add some more tanks. Chain to the outer wheels also went in today, up until now it has been ruining with only the middle 4 wheels working (8wd)
|