MichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant future
Re: Building the Structure of the Robot?

Quote:
Originally Posted by ksafin View Post
OK.

Say we obtain a sponsor that can do various fabrication, waterjet cutting, CNC machining, etc.

At that point I have another question. Our team organization is based around the fact that everyone works with what we have and is contributing to an assembly.

With most of the design/assembly itself being done in CAD and then sent off, what does the mechanical team do? In essence, if the drivetrain is being made in CAD and made my a sponsor, what does the actual mechanical team do while the design team is CADing it and sending it off?
If you still plan to do in house work(as Adam said it can be very hard to not do any in house work) then they can start machining things. However there should still pe a primary emphasis on CAD and prototyping during the first few weeks of build.
__________________
Team 1836 - The Milken Knights
2013 LA Regional Champions with 1717 and 973
2012 LA Regional Finalists with 294 and 973
To follow Team 1836 on Facebook, go to http://www.facebook.com/MilkenKnights
To go to our website, go to http://milkenknights.com/index.html