MichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant futureMichaelBick has a brilliant future
Re: Building the Structure of the Robot?

Week 1: Preliminary Design, Prototype, have a CAD for the drivetrain done by at least the end of this week(preferably earlier) so that you can start to/send out parts to be machined at the end of the week.

Week 2-3: CAD and machine parts as you finalize the CAD

Week 4: CAD is done. Finish up machining by the end of the week so that you can assemble the robot during the weekend.

Week 5-6: Program and ITERATE!

Feel free to adjust this schedule to your team, but you should definitely have at least a week before you bag the robot to program and iterate.
__________________
Team 1836 - The Milken Knights
2013 LA Regional Champions with 1717 and 973
2012 LA Regional Finalists with 294 and 973
To follow Team 1836 on Facebook, go to http://www.facebook.com/MilkenKnights
To go to our website, go to http://milkenknights.com/index.html