Re: Build Season Schedule
Our build season plan is based on 1114's, note that the one I'm posting is not our final schedule for build season, it's still being changed but hopefully it gives you an idea of how to plan your season.
days 1-4: brainstorming, what do you want your robot to do? How do you want your robot to do it? These are the two most important questions that should drive your entire brainstorming process.
day 5: design freeze
days 5-8: prototyping, electrical layout on drive-base
days 5-14: build drivetrain, programmer begin coding for drive train
days 8-14: robot controls, finish drivetrain
day 15: begin autonomous coding
days 8-21: mechanism construction, programmers finish drive train code
days 22-28: mechanism integration with drive base, wiring
day 29: robot finished
days 29-40: testing, driver training, fixing, perfecting
Remember, a good driver always beats a good robot
Note: practice bot construction happens in parallel with competition bot construction.