Answer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud ofAnswer42 has much to be proud of
Re: Back for more..VEXpro 2014 Product Unveiling

Quote:
Originally Posted by Paul Copioli View Post
All of the components for the 3 CIM Ball shifter are in our assembly facility here in Greenville. They are currently being inspected and kitted. We are pushing to have these shipping this week.

We got started on the manufacturing of the WCP items a little later than we wanted. Both WCP and VEX are pretty particular about design details so we released the drawings to production later than we wanted. The dates on the VEXpro website for the WCP items are still our expected ship dates. Please note that this is an initial inventory problem only. Once the items arrive, WCP, The Robot Space, and VEX will have plenty of inventory for the entire 2014 season.



We are working on the application drawings for this and should have them by the weekend.