Anyone else having issues with suppliers/vendors and their significant delays? My team placed an order on Saturday, and the order was packed 9pm thursday, actually picked up from vendor at 7pm friday. With two day shipping it arriving on Tuesday....
We even placed an order from a different supplier, same day much farther away and got those parts last week.
From the manual:
Quote:
C. must be able to ship any general (i.e., non-FIRST unique) product within five business days
of receiving a valid purchase request. It is recognized that certain unusual circumstances
(such as 1,000 FIRST Teams all ordering the same part at once from the same VENDOR) may
cause atypical delays in shipping due to backorders for even the largest VENDORs. Such
delays due to higher-than-normal order rates are excused.
|
Still feel as if this is a very long time.