Quote:
Originally Posted by sanddrag
Andrew, you say you had build days on MWF and Sat. Did the team still meet on the other three days of the week or did you really meet only 4 days per week?
|
We were very conscientious about only meeting those 4 days until week 6. We met more during the final week of build, went back to the 4 day schedule, and then did more like 5-6 as we got deeper into the season. We tried to make sure we left at 11 pm at the latest most nights, which we did a reasonably good job of during the build period and a less good job of as we got into competition season.
On the whole it was much better than previous years in which we worked 7 days a week the entire season, often until 2 am or later every Friday/Saturday.