Re: Team Structure and Build Schedule
I'll offer the general comment that you should allocate more time for most things that you have on there. For instance you only 1 week of actual robot programming. Often programming projects work by programming small chunks at a time, testing them, and them moving on. Other times people try to write a bunch of code up front and then do a bunch of testing afterword (not what I recommend). But either way there will be a ton of code writing all throughout the process. Considering that you are teaching students week 1, I might allocate 3 or 4 weeks to programming on the actual robot.