Originally Posted by falconmaster
Ok , I guess I am missing something here. In the team update 2 why are there two knots in the Rope Anatomy diagram in Fig 9-2?
Also is the end with the loop, showing an option that you could use a loop or a straight piece with fraying prevention?
|
one knot is required (to hang from the DAVIT). the other knot is optional, and can be no closer than shown in the diagram to the davit knot. the number of optional knots is from 0 to N where N is unknown, but large.
the loop on the end is made using a segment of the rope, as a result, the end with fraying prevention is not part of the loop. since the loop is longer than the fray-prevented part, the loop constitutes the end of the rope for the purpose of length measurement.
__________________
Student FRC23 (1996-1999), Mentor FRC246 (2000), Mentor FRC1318 (2007-2009), Mentor FRC93 (2011), Mentor FRC2151 (2012), Mentor FRC23 (2013), Mentor FRC4761 (2014-2017)
1998 - National Chairman's Award and Woodie Flowers Award (FRC23, Mike Bastoni ) | 2007 - PNW SF (488, 1595) | 2008 - Oregon RCA - Seattle #2 Seed, SF (488, 1696) | 2009 - Oregon #1 Seed, Winners (1983, 2635) - Seattle SF (945, 2865) - Galileo #2 Seed, SF (973, 25) | 2012 Midwest F (111, 71) | 2014 RIDE Winners (78, 125), Inspector - NEU #24, QF (3479, 3958) - NECMP #35 | 2015 Reading #11, SF (1058, 190), Inspector - RIDE #17, QF(4055, 5494), Inspector - NECMP #57 | 2016 Reading #4, SF (133, 4474), DCA, Inspector - Ride #22, SF (1735, 2067), Creativity, Inspector - NECMP #48, RCA - Archimedes
|