- Have a final realistic conceptual design by day 5
- Be using calipers by day 8
- Bring out the drills and saws by day 10
- After the above, treat every day like it's your last day.
- Everything can and will take longer than expected.
- Nothing will get done early
- Keep a large chart of tasks to be accomplished with start and finish times and who is responsible for them. A large "white board" is a good place for this (and for many other things)
Good Luck!
__________________
Teacher/Engineer/Machinist - Team 696 Circuit Breakers, 2011 - Present
Mentor/Engineer/Machinist, Team 968 RAWC, 2007-2010
Technical Mentor, Team 696 Circuit Breakers, 2005-2007
Student Mechanical Leader and Driver, Team 696 Circuit Breakers, 2002-2004
|