View Single Post
  #3   Spotlight this post!  
Unread 23-01-2004, 13:10
Unsung FIRST Hero Woodie Flowers Award
Chris Fultz Chris Fultz is offline
My Other Car is a 500 HP Turbine
FRC #0234 (Cyber Blue)
Team Role: Engineer
 
Join Date: Jan 2002
Rookie Year: 1942
Location: Indianapolis, IN
Posts: 2,837
Chris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond reputeChris Fultz has a reputation beyond repute
Re: Cyber Blue Program Review Process

Last night was the Preliminary Design Review.
Cyber Blue had five reviewers - 3 common to the Concept Review and one
new reviewer from each of two other sponsors.

The presentations were made by several of the team members.

Overall the reviewers were positive about the progress made in the past week and how many of their ideas and comments had been considered.

We spend a great deal of time discussing the schedule and risk assessment and mitigation activities. Their comments would apply to any team, so I will share them here.

1. Quickly identify the longest lead* components. Make a priority list based on lead time. Assign drafting jobs based on the longest elad items. Make sure someone is defining the specs and placing orders for purchased parts.

2. Determine if some long lead manufactured parts can be 'risk released'. This would mean releasing the print to the manufacturing team before it is completely finished. This would allow the manufacturing team to begin working on the part up to a specific point while the design work continues.

3. Determine a method of easy priority for manufacturing work. Color coded drawings or a numbering system would make it easy for the machining team to know what part should be worked on next. It is probably not a first in - first out priority.

4. Write basic routings for manufactured parts and have the machinist mark progress. That way, if someone is absent the next work period someone else can easily see what needs to be done and finish the work.

5. Identify critical dimensions and locations so that the machinist knows where accuracy is absolutely required and where there is some margin room.

Next week is the Critical Design Review. We should have completed drawings and a full risk assessment and several parts / sub-assemblies completed.

* Lead time is the time to either design and manufacture the part or the time to spec and purchase and take delivery of the part.










100.
__________________
Chris Fultz
Cyber Blue - Team 234
2016 IRI Planning Committee
2016 IndyRAGE Planning Committee
2010 - Woodie Flowers Award - Championship