Quote:
|
Originally Posted by Felipe Reis
In order to do that you need to put each Backburner Server into the same Manager..... so when you submit a job both CPUs will work as one....
Felipe
|
I though that is what I did, here is exactly what I did:
Started the manager on my computer.
Started the server on my computer
Started the server on another computer
The manager registered both systems
I submitted the task from my system.
the task got assigned to my system only, it said the other system was idle. I tested it by submitting another task before the first one was finished, then it assigned the seconed task to the other computer.
What did I do wrong?
Thank you very much!