Thread: Build Timeline
View Single Post
  #1   Spotlight this post!  
Unread 01-01-2008, 20:51
Tim Baird's Avatar
Tim Baird Tim Baird is offline
Design Ninja
FRC #0126 (Gael Force)
Team Role: Engineer
 
Join Date: May 2001
Rookie Year: 1999
Location: Clinton, MA
Posts: 241
Tim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond reputeTim Baird has a reputation beyond repute
Send a message via AIM to Tim Baird
Re: Build Timeline

We typically follow this:

week 1: brainstorm and mockup
week 2: finish brainstorming and mockups
week 3: finalize designs and start building
week 4: build
week 5: build
week 6: finish building, tweak, test, tweak, break, fix, ship.

week 7: check to see if the pets are still alive, ask significant others to take us back, do 6 weeks worth of make-up homework, and ask my boss for another extension.
__________________
Tim Baird
FRC Alum and FRC/FLL Volunteer
Project Engineer @ Nypro

History:
Gael Force 126: 1999-2000
WPI 190: 2001-2004
Gael Force 126: 2005-2010
Event Volunteer Only: 2011-Present
Reply With Quote