Quote:
Originally Posted by Wayne Doenges
Al, correct me if I'm wrong. The B.O.M. is mostly the extra parts and pieces you buy/get donated above the KOP parts.
The custom made parts you need to have the mentor estimate what the parts are worth.
If you buy a 10' long piece of steel but only use 2' than divide the 10' piece price by 5 to get the correct BOM price.
|
Wayne, the example 10' long piece has to be counted as 10' for cost accounting unless the same stuff is available in 2' lengths. It's prorated on smallest available commercial quantity (that works...

), not on how much you use. The example given in the rulebook is a 10" x 10" piece of material, cut from an 4' by ??' sheet, but available commercially in 1' by 1' sheets.
(Sorry, I'm not Al...)

__________________
Past teams:
2003-2007: FRC0330 BeachBots
2008: FRC1135 Shmoebotics
2012: FRC4046 Schroedinger's Dragons
"Rockets are tricky..."--Elon Musk