Re: Breakdown of 6 week schedule
What our team typically does:
Week 1: Analyze the rules, figure out how the game might play out, talk about strategy, discuss robot attributes we want, figure out how one might incorporate those attributes into a robot, figure out what attributes are most important
Week 2: Prototype different mechanisms for the robot, begin to test and compare them
Week 3: Practice with different prototypes, decide on what is the best and will be used for final robot
Week 4: Practice with "winning" prototype, figure out what changes to make, begin constructing final robot
Week 5: Constructing and practicing with final robot
Week 6: Practice lots- use this to test and tweak final robot. Attend a pre-ship scrimmage, make any last changes to the robot based on this experience.
Then ship it!
This is a good general guideline to go by, but every team does it differently, so it is by no means the only way. Good luck!
__________________
Ellen McIsaac
Team 1124 ÜberBots 2005-2015
Team 5012 Gryffingear 2015+
Last edited by smurfgirl : 05-01-2009 at 00:36.
Reason: forgot to mention scrimmage (:
|