Re: Bridge problems?
Posted by ChrisH at 04/10/2001 11:28 AM EST
Engineer on team #330, Beach 'Bots, from Hope Chapel Academy and NASA JPL, J & F Machine, Raytheon, et al.
In Reply to: Bridge problems?
Posted by Elliot Johnson on 04/09/2001 11:25 PM EST:
The bridge we used at LA and San Jose (it was the same one) was "sticky". It was hard to move and was not truly tristable. It would often balance with the edge 2 or three inches off the floor. I think FIRST reworked the bridges after the regionals to loosen them up. Maybe they went too far?
Chris Husmann,PE
Team 330 the Beach'Bots
__________________
This message was archived from an earlier forum system. Some information may have been left out. Start new discussion in the current forums, and refer back to these threads when necessary.
|