View Single Post
  #5   Spotlight this post!  
Unread 19-01-2010, 16:01
Gary Dillard's Avatar Unsung FIRST Hero
Gary Dillard Gary Dillard is offline
Generator of Entropy
AKA: you know, the old bald guy
FRC #2973 (The Mad Rockers)
Team Role: Engineer
 
Join Date: Nov 2001
Rookie Year: 1998
Location: Huntsville, AL
Posts: 1,584
Gary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond reputeGary Dillard has a reputation beyond repute
Send a message via AIM to Gary Dillard
Re: 24V rule change implications?

Quote:
Originally Posted by EricVanWyk View Post
Your supporting statements are correct, but your main conclusion is not.

It is absolutely true that a single solenoid breakout can only supply a single voltage to ALL of its 8 channels.

However, you are not forced to only use all 12V or all 24V. Spike Relays are still legal and can control 12V solenoids (not 24V). Also, the 2010 image supports two solenoid breakouts, which may run at separate voltages if desired. "Mixed Mode" is well supported.
Yeah, I knew those were options; just wanting to see if I understood how the solenoid breakout worked versus buying and adding stuff to the control system. Our second year team doesn't have alot of Spikes and solenoids laying around like SPAM did. Thanks.
__________________