|
|
|
![]() |
|
|||||||
|
||||||||
![]() |
| Thread Tools | Rate Thread | Display Modes |
|
#16
|
|||||
|
|||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
|
|
#17
|
||||
|
||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
Last edited by Cash4587 : 26-12-2015 at 23:25. Reason: Clarification |
|
#18
|
||||
|
||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
|
|
#19
|
||||
|
||||
|
Re: pic: Recycle Rush Re-design Part 2
I would have to see it to believe it. I mean I don't doubt that it could be done but given the angle that the totes are entering the field, my team had to have a travel of about 25 inches in order for the tote being lifted to not interfere with the tote coming in through the chute. If we didn't lift it high enough the tote above it would be pushed past the point of being locked in place with the lip on the tote below it.
|
|
#20
|
||||
|
||||
|
Re: pic: Recycle Rush Re-design Part 2
In long distance power transmission, a transformer is used to increase voltage to crazy high amounts. This reduces the power-loss and means that a less thick wire is required.
Obviously no custom circuitry can generate voltages greater than 24 volts, but is there anything stopping a transformer being used to increase the voltage at the motor controller, to compensate for the voltage lost during transmission. As long as it decreased down to 12 volts at the motor, it would still be being fed by 12 volts thus one motor controller "R44 CUSTOM CIRCUITS shall not directly alter the power pathways between the ROBOT battery, PDP, motor controllers, relays, motors, or other elements of the ROBOT control system (items explicitly mentioned in R55). " Does increasing voltage alter the power pathways? |
|
#21
|
|||||
|
|||||
|
Re: pic: Recycle Rush Re-design Part 2
Let's start with a 7 gal (1617 cu in) charged to 117.6 psig (that's +8atm, selected to simplify the math). As we regulate this down to 58.8 psig (+4 atm), we are making 1617 * 4 = 6,468 scfm, or 1,293 cu in at +4 atm (58.8 psig). Multiplying this out, I show a potentially usable energy of over 76,000 lb-in. A tote weighs 7.8 lb, so that's about 9,750 tote-inches, or 5 totes times 1950 inches. If each lift is 25", this is still a total of 78 lifts. That's 78 lifts of 5 totes 25 inches. There were only 30 totes behind the walls, so even without doing any optimization beyond not pressurizing the down stroke, there is more than twice the required energy in one 7 gal tank to stack all of the totes behind the wall. (Though I haven't done any flow calculations to determine if it can be done in 2:15!)
With a 10 pound air tank, this obviously won't get down to 15 pounds, but I expect that it can be done for well under the available 35 pounds, including tank, cylinders, frame, tether, and electronics. |
|
#22
|
|||||
|
|||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
Quote:
Quote:
Last edited by GeeTwo : 27-12-2015 at 01:14. |
|
#23
|
||||
|
||||
|
Re: pic: Recycle Rush Re-design Part 2
Thanks for clarifying the meaning of Power pathway. I thought that it meant that must be a direct pass-through without being interrupted by a sensor or relay etc. I was taking it in a rather literal sense.
|
|
#24
|
||||
|
||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
Also, if you did what many teams did this year and let the second tote fall into the first one without lifting the first one, you will only need to lift 4 totes per 6 stack, not 5. You also won't need to lift them as high, only from 1 tote high to above the chute instead of from the ground. IIRC that's less than 25". Or you could do what we did and build a ramp attached to our stacker for the totes to slide to (almost) ground level, then you only need to lift the height of one tote. |
|
#25
|
|||||
|
|||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
Quote:
Quote:
Last edited by GeeTwo : 27-12-2015 at 22:15. Reason: fixed close quote |
|
#26
|
||||
|
||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
|
|
#27
|
|||||
|
|||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
If you were thinking of leaving a tote on the floor the whole time, that would be lifting 10 totes a bit over half as far as the six above. It's probably a wash in terms of air, but two lifts should take less time than four. Last edited by GeeTwo : 27-12-2015 at 22:48. |
|
#28
|
|||||
|
|||||
|
Re: pic: Recycle Rush Re-design Part 2
Quote:
|
|
#29
|
||||
|
||||
|
Quote:
Last edited by mman1506 : 28-12-2015 at 12:17. |
|
#30
|
|||||
|
|||||
|
Re: pic: Recycle Rush Re-design Part 2
That would be "leaving the downstroke unpowered", which has been considered and largely discarded. Unless you have a separate mechanism to engage and disengage from the tote, your downstroke will have to work against some sort of spring action to get around the top edge of the tote. For reliable action, either the down stroke needs to be powered, or a spring return is needed, or the carriage must be heavy enough to force through the ratcheting action.
|
![]() |
| Thread Tools | |
| Display Modes | Rate This Thread |
|
|