How long did it take for you to build your drivetrain?
I was wondering, exactaly how long did it take for your team to build your drivetrain for (any of) your previous robots? How many days? Total hours? Even including the time it took to order parts or get them custom fabricated?
Thanks, -Jonathan |
|
#2
|
|||||
|
|||||
|
Re: How long did it take for you to build your drivetrain?
I believe last year 1293 took about five weeks to finally get the drivetrain to a point where it would actually drive. Now, that was including switching motors three times that I can think of (CIMs, Drills, and window motors), so I think next year our time will be much improved.
|
|
#3
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
it would have taken us a week and a half if the machine shop we worked with were stuck to the time table they gave us, but instead it took about 3 weeks.
|
|
#4
|
|||||
|
|||||
|
Re: How long did it take for you to build your drivetrain?
Last year 862 took up the whole 6 weeks of build season to build our Tri-star system that includes pulling the drive train out twice once even tearing it completely apart then rebuilding it the next day. Then the last two days of build we decided that the Tri-stars wouldn't work. And we started work on Plan B: designing and building a new 4 wheel drive train into a frame built for the Tri-star system. We ended up shipping Loki with the Tri-stars still on him. It took all of about three hours on the practice day at Great Lakes to install the new drive train which worked very well needing only some minor tune ups thought the competition season.
|
|
#5
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
Building a drivetrain is not so much a matter of how long, but rather of team coordination. I would contend that you cannot have a consistently good robot without equally good teambuilding. In order to make an original gearbox for example, you really should be streaming or subteaming your human capital. I thought of it sort of like an economic model while I was a student with a building and leadership role. If you don't specialize, you can still make a great robot but you can also say goodbye to a really good drivetrain for the simple reason that multiple tasks performed by the majority of the group in order put too much pressure on the group. There will of course be an opportunity cost of specialization (a perfect function might be forgone by allocating 30% of your students to making a good drivetrain), but the final yield will be much greater.
Let's go by Billfred's example. Even though most teams don't take quite that long to make a drivetrain, if you were to syphon off 30% of your students to a hierarchical subteam for mobility (or whatever the optimal percentage you might find to be), robot building gets a lot easier. New Canadian teams for example are encouraged by 188 to use our old team model of dividing the majority of the team into two subteams of Function and Mobility (the rest might be part of a publicity or fundraising group). We have since heavily tweaked this model, but it's a good starting point. As for some tips about how to speed up your drietrain's construction, a look into the rules will help you out (disclaimer: they can and do change at the start of every season). For example, you can order certain materials and parts ahead of time and design your gearbox on CAD software before the build period even starts. Most veteran teams have this pre-build process mastered. In our case, the actual construction of our tranny/gearbox took nearly five weeks. Considering we hand-machined all our parts, that's rather good, I think. Still, the real gains you can make in terms of time to build your drivetrain are more in adminstration than technics and tools. |
|
#6
|
|||
|
|||
|
Re: How long did it take for you to build your drivetrain?
well as a rookie team we used the kit pieces to make a 4wd robot and it took maybe a week to finish it, and then later on about 2 days more to add the system to switch between 4 and 2 wheel drive
|
|
#7
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
good point, Jonathan.
But for some teams, like us, organizing all of the team members isn't as easy as we hope it to be. Mainly, we have a mentor who likes to challenge and argue about every single design created, unless he created it himself or he helped create it. So right now I'm trying to search for some hard-evidence to show that certain types of drivetrains can be built within the build period. |
|
#8
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
Quote:
Team 188 is no different. Just ask any of them. Hmmmmm I wonder who that mentor is. Challenging is good because if you can't explain the reasoning then perhaps not enough went into it. Remember that the mentor has gone through the processes himself and know his/her reasoning. He/she doesn't know yours and needs to build confidence in your thought process. It would be good to question their ideas to learn from them or to see if they really thought their process through. Don't spend too long on building any part of your robot. This can cause problems on the team and there won't be time to test before ship. |
|
#9
|
|||||
|
|||||
|
Re: How long did it take for you to build your drivetrain?
Just like Jonathan said earlier It doesnt matter how long does it take to make the drive train. I personally believe in efficiency of the product, not how much time it took to me to build it. Last year it took us a good 3 weeks to get done with two of the transmission. but I have learned a lot of things. you should concentrate on every single aspect of the robot when you have only 6 weeks to finish it. concentrating on one aspect (drive train) and not the other (mechanisms, others) may give you a lot of problems at the end of 6 weeks. it was proven to me last year. Drive train is one important part of the robot as well as other parts of the robot are very important too. team 108 is ready to roll and we like challenges (ask any team who were at Midwest and Nationals (in galilio division), they will tell you) for 2005 season. Now only if dave would give us the game hint...
![]() |
|
#10
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
We like to get the drive-system out of the way first and it would be done in about 2-3 weeks. But the transmision took us FOREVER last year. The problem we were hung up on was trying to figure out how to make all 3 gears shift accurately. I think we spent several days trying to make the shifting mechenism work.
|
|
#11
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
We use the same drive train as past years. I hope it will be the same this year. If you have something that works use it. You don't have time at this point to re-invent the wheel.
|
|
#12
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
Last year, we spent most of the 6 weeks designing the drive train. This didn't work out so well since we didn't have any working special features. Granted, we had a very good drive train, but special features are nice to have. Things we have decided to do differently this year:
-we've done more brainstorming during the off-season -we plan on doing the brainstorming differently and decide on a drive train and design it during the first week, so that it can be built with time to spare in testing and practicing driving for the last week of the build season -we weren't organized enough for brainstorming last year and didn't meet oftne enough during the first week So that's what we plan to do differently to hopefully spend less time on a drive train and more time on special features. |
|
#13
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
Here has been my history with drivetrains in FIRST…
In 2000, as a junior on Team #258, we completed our drivetrain in three weeks. It was a simple 4wd chain and belt driven system run by the ole 3/8” drill motors. The reason it wasn’t completed earlier was because we had very few members of the team, and were working simultaneously on the ball mechanism and drivetrain. In 2001, as a senior on Team #258, we built pretty much the same 4wd drivetrain as 2000 (but completely with chain and sprockets) in 2 weeks. In 2002, as a college student on Team #258, we built a 2-speed shift on the fly sprocketbox drivetrain powered by just the CIM motors in 3 weeks, and then spent another week lightening it up significantly. In 2003, as a college student on Team #258, we spent the first week and a half designing our swerve drive system powered by both 1/2” drill motors and the CIM motors (and rotated by the Globe motors), and then we didn’t complete it until about a week before ship date. We took our time on it because, since it was a simple game, we didn’t really have any other mechanism on the robot. We ghetto-rigged some wings on Thursday of SVR. If we had really tried we could have had the swerve designed in half a week, and then had it completed somewhere along the third week. In 2004, as a college student on Team #258, we spent about a week and a half designing our “stretcher-drive” system powered by the 1/2” drill motors, and finished it about a week from shipdate. We would have finished it earlier had we had more than 3 people machining parts along with parts we outsourced to a machine shop. There was a crapton of machining on that robot for a team of just a handful of us. It was a lot of fun to work on, though, looking back on it. |
|
#14
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
Quote:
|
|
#15
|
||||
|
||||
|
Re: How long did it take for you to build your drivetrain?
Quote:
|
![]() |
| Thread Tools | |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Where do you actually build your robot and who does the building??? | Elgin Clock | General Forum | 47 | 14-11-2006 17:50 |
| OCCRA Teams - where do you build? | Phil 33 | OCCRA | 7 | 28-10-2004 21:41 |
| Northrop/FIRST | Redhead Jokes | General Forum | 9 | 20-09-2004 12:24 |
| How long should production time be??? | archiver | 1999 | 4 | 23-06-2002 23:16 |