Chris,
Thanks for sharing your schedule. It's good to compare task durations with other FRC teams.
Does 2013 revision 2 represent the actual activity dates or your 2013 pre-season plan? Did you miss any key milestones if this only represented your plan?
We finished our 2013 robot on time, but missed several interim milestones. In the end, it was not a significant impact, but we would have preferred more practice time before bag day.
Thanks,
David
|