After looking into how to strategize, design, and build quicker during build season, I came across a bunch of 1678 workshop videos from last year and this year that got straight to what I was looking for, here is the link to the ones Iâm referencing:
(2016) https://www.youtube.com/watch?v=MW6KqtDR9_U
(2017) https://www.youtube.com/watch?v=SVacrE4sKig
One part of the video really intrigued me, but got me slightly confused. In the 2017 video, at 34:30, he states that by Day 3 the drivetrain design is done. So I understand that 3 days is more than enough time to design a WCD, but what I dont understand is how you adapt your other mechanisms to fit ontop your drivetrain if it is already out to build? Looking at their GrabCad renders:
https://grabcad.com/library/pomelo-pummeler-frc-team-1678-2017-1
It seems 1678 had their intake gap already added, so is that a decision you have to make pretty much day 2? Also, do you just add a bunch of holes and mount everything to those preset holes? If anyone (possibly even someone from Citrus Circuits) could shine some light on this that would be awesome, I would really like to start manufacturing as early as possible next season ::ouch::